Sample Questions

# Chapter Title Question
1 Plumbing, Pipes, Water Pressure and Pipe Fittings How many feet must a disposal field trench be from a dwelling?
2 Plumbing, Values and Gas Piping Why are pipes carrying steam and hot water insulated?
3 Plumbing, Values, Drainage, Vents and Sandpipes Steel fittings used in a water piping system within a building must be _________.
4 Plumbing, Septic Tanks, Drainage and Gas Lines The combustion chamber of a gas fired water heater installed in a private garage must be above the floor at least ________ inches.
5 Plumbing, PSI, Water Pressure, Water Flow and Pipelines The size of any required water supply pipe depends on what?
6 Plumbing, Valves, Water Heaters, Gas Pipes, Oxygen and Gas Cylinders All manholes must be equiped with _________.
7 Plumbing, Appliances, Drains, Fixtures and Inspections __________ is exempt from drainage system rough in testing.
8 Plumbing, Installation and Repairs When is a plumbing permit not required?
9 Welding, Blazing, Arc, Oxyacetylene, Testing and Inspection What is the junction of the weld metal and base called?
10 Mathematics, Calculations and Formulas

P = amount earned by plumber 
A = amount earned by assistant 

If the plumber makes $32 per hour and he worked two hours more than his assistant, then 2(32) = $64 

P = A + 64 
P + A = 314 

Now replace the P in the second equation with the first equation, like so 
(A + 64) + A = 314 
which can be rewritten as 
2A + 64 = 314 
subtract 64 from both sides of the equation 
2A = 250 
divide by 2 on both sides of the equation 
A = $125 <==== that's how much the assistant earned 

Now use that $ amount in either or both of the original two equations to find P 
P = (125) + 64 
P =

12 Labors, Employees, Contractors, Insurance and Safety Upon request by the prime contractor, the subcontractor is responsible for submitting faithful ____________.
13 Bid Preparation and Estimating The notice to owner contained in a contract, informs the customer of _________________.
14 Basic - Estimating, Blueprint Reading and Plans A revision (marker) is shown on the completed set of working drawings by _______________.
15 Safety and (Dig Alert)

In reference to section 1926.1101(f)(2)(iii)(B), Where the employer has monitored ____________ asbestos jobs for the PEL and the excursion limit within 12 months of the current or projected job, the monitoring and analysis were performed in compliance with the asbestos standard in effect; and the data were obtained during work operations conducted under workplace conditions "closely resembling" the processes, type of material, control methods, work practices, and environmental conditions used and prevailing in the employer's current operations, the operations were conducted by employees whose training and experience are no more extensive than that of employees performing the current job, and these data show that under the conditions prevailing and which will prevail in the current workplace there is a high degree of certainty that employee exposures will not exceed the TWA and excursion limit; 